Owner View · QA-LMT-2024-018
Lusail Marina Tower
Qatari Diar · Lusail, Qatar · QAR 2.4B
62% Complete+2.1d vs baseline94% budget usedZero LTIs
87Health
62Progress
Contract Value
QAR 2.4B
94% committed
Earned Value
QAR 1.48B
SPI 0.97
Days Remaining
486
Baseline +2d
Safety Index
A+
0 LTI / 1.4M hrs
Master Schedule
6 milestonesSubstructure
Jul 2024 · Complete
Superstructure
Mar 2026 · On track
MEP Rough-In
Aug 2026 · +2d slip
Façade
Nov 2026 · On track
Fit-Out
Apr 2027 · Not started
Handover
Sep 2027 · Not started
Health Trend+6.2%
Pending Owner Approvals
3- VAR-014Due 2dLobby stone selection — change orderQAR 1.2M
- PAY-022Due TodayProgress payment #22QAR 48.6M
- EOT-003Due 5dFaçade EOT request — 14 daysSchedule
Portfolio rollup
3
Active
1
Planning
2
Closeout