Portfolio overview
Construction projects
Live site map, durations, budgets and progress across 2 projects.
Active
1
In planning
1
Avg. progress
38%
Open items
20
17 RFI · 3 NCR
Site map· 2 sites
Loading map…
Lusail Marina Tower
LMT-2024 · QAR 1.42B · Lead Ahmed Karim
Mixed-use marina tower — 78 floors, podium retail, 3 basement levels.
Progress
62%
-7% vs schedule
Schedule
69%
840 / 1216 days
Budget used
58%
QAR 1.42B contract
Open items
15
12 RFIs · 3 NCRs
Schedule timeline
43 months · 9 phasesPhase
Design & DD
AECOM
Authority permits
Client PMO
Substructure
ALEC
Superstructure (L1–L78)
ALEC
Façade install
Permasteelisa
MEP rough-in
Drake & Scull
Interior fit-out
Depa
T&C / Commissioning
Hilson Moran
Handover & DLP
Client
Jan 24
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan 25
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan 26
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan 27
Feb
Mar
Apr
May
Jun
Jul
Today
100%Done
Design & DD
Design · AECOM
Start
Jan 15, 2024
End
Jun 30, 2024
Duration
167 days
Progress
100%
100%Done
Authority permits
Permits · Client PMO
Start
May 01, 2024
End
Aug 15, 2024
Duration
106 days
Progress
100%
100%Done
Substructure
Substructure · ALEC
Start
Jul 01, 2024
End
Dec 20, 2024
Duration
172 days
Progress
100%
72%In progress
Superstructure (L1–L78)
Superstructure · ALEC
Start
Dec 01, 2024
End
Mar 30, 2026
Duration
484 days
Progress
72%
28%In progress
Façade install
Façade · Permasteelisa
Start
Aug 01, 2025
End
Aug 30, 2026
Duration
394 days
Progress
28%
18%In progress
MEP rough-in
MEP · Drake & Scull
Start
Oct 01, 2025
End
Dec 15, 2026
Duration
440 days
Progress
18%
0%Upcoming
Interior fit-out
Fit-out · Depa
Start
Jun 01, 2026
End
Mar 30, 2027
Duration
302 days
Progress
0%
0%Upcoming
T&C / Commissioning
Commissioning · Hilson Moran
Start
Nov 01, 2026
End
May 31, 2027
Duration
211 days
Progress
0%
0%Upcoming
Handover & DLP
Handover · Client
Start
May 01, 2027
End
Jun 30, 2027
Duration
60 days
Progress
0%
DoneIn progressDelayedUpcoming Today Milestone (done) Milestone (upcoming)
Milestones
- Substructure completeDec 15, 2024
- Tower L40 castSep 30, 2025
- Façade dry-inApr 15, 2026
- MEP commissioningJan 20, 2027
- HandoverJun 30, 2027
Timeline
StartMar 01, 2024
EndJun 30, 2027
Duration1216 days
Elapsed840 days
Parties & team
ClientQatari Diar
Main contractorHamad Bin Khalid Construction
Subcontractors4
Team members12
Location
SiteLusail, Qatar
Coordinates25.3833, 51.4900
4 subcontractors 12 team members